Commissioning Phase 1

 

Commissioning Phase 1: Status (Active WPs)

System Sub-system EDMS Page WP Start Date Sign off Issues from analysis
Inner detector   ID Phase 1        
  SCT          
  TRT          
  Pixel          
Tiles Calorimeter   Tiles Phase 1        
      WP 2.1 Cables installation step 1 1-Apr-05 1-Jun-05  
      WP 3 Rack electronics USA15 1-May05 31-Aug-05  
      WP 4.1 F/E Electronics on Truck (Mobidick) 7-Mar-05 1-May-05  
      WP 4.2 F/E Eletronics on truck (MobiDAQ)      
      WP 8.1 Cesium Calibration system (pipes) 1-Jan-05 1-May-05  
LAr Calorimeter   LAr Phase 1        
      4.1 F/E electronics on truck: infrastructure 25-jan-05 9-Mar-05  
             
Muons Barrel   Muons Phase 1        
      WP X: installation sectors 12 and 14

 

     
      WP Y: Sector 13 1-May-05 31-Aug-05  
Central DCS/DSS   DCS/DSS Phase 1        
      WP 1 LCS DCS USA15      
      WP x DSS USA15      
TDAQ            
  DAQ          
      Pre-series      
      WP 1 DAQ infrastructure      
      WP2 ROD crate DAQ      
      WP 3 ROS