Commissioning Phase 1
Commissioning Phase 1: Status (Active WPs)
System | Sub-system | EDMS Page | WP | Start Date | Sign off | Issues from analysis |
Inner detector | ID Phase 1 | |||||
SCT | ||||||
TRT | ||||||
Pixel | ||||||
Tiles Calorimeter | Tiles Phase 1 | |||||
WP 2.1 Cables installation step 1 | 1-Apr-05 | 1-Jun-05 | ||||
WP 3 Rack electronics USA15 | 1-May05 | 31-Aug-05 | ||||
WP 4.1 F/E Electronics on Truck (Mobidick) | 7-Mar-05 | 1-May-05 | ||||
WP 4.2 F/E Eletronics on truck (MobiDAQ) | ||||||
WP 8.1 Cesium Calibration system (pipes) | 1-Jan-05 | 1-May-05 | ||||
LAr Calorimeter | LAr Phase 1 | |||||
4.1 F/E electronics on truck: infrastructure | 25-jan-05 | 9-Mar-05 | ||||
Muons Barrel | Muons Phase 1 | |||||
WP X: installation sectors 12 and 14
|
||||||
WP Y: Sector 13 | 1-May-05 | 31-Aug-05 | ||||
Central DCS/DSS | DCS/DSS Phase 1 | |||||
WP 1 LCS DCS USA15 | ||||||
WP x DSS USA15 | ||||||
TDAQ | ||||||
DAQ | ||||||
Pre-series | ||||||
WP 1 DAQ infrastructure | ||||||
WP2 ROD crate DAQ | ||||||
WP 3 ROS |